Title: | Break-even analysis and size optimization of a PV/wind hybrid energy conversion system with battery storage - A case study | Authors: | Ekren, O. Ekren, Banu Yetkin Ozerdem, B. |
Keywords: | Break-even analysis Hybrid energy Optimization Response surface methodology Simulation Base stations Cost accounting Electric batteries Electric lines Energy conversion Global system for mobile communications Industrial management Mobile telecommunication systems Surface properties Wind turbines Electricity networks Electricity-consumption Global system for mobiles Izmir Institute of Technology Electric network parameters comparative study design energy use numerical model optimization storage wind turbine Eurasia Izmir [Turkey] Turkey |
Publisher: | Elsevier Ltd | Abstract: | This paper aims to show an optimum sizing procedure of autonomous PV/wind hybrid energy system with battery storage and a break-even analysis of this system and extension of transmission line. We use net present value (NPV) method for the comparison of autonomous hybrid energy system and extension of transmission line cases. The case study is completed for the satisfaction of the electricity consumption of global system for mobile communication base station (GSM) at Izmir Institute of Technology Campus Area, Urla, Izmir, Turkey. First, we optimize the PV/wind energy system using response surface methodology (RSM) which is a collection of statistical and mathematical methods relying on optimization of response surface with design parameters. As a result of RSM, the optimum PV area, wind turbine rotor swept area, and battery capacity are obtained as 3.95 m2, 29.4 m2, 31.92 kW h, respectively. These results led to $37,033.9 hybrid energy system cost. Second, break-even analysis is done to be able to decide the optimum distance where the hybrid energy system is more economical than the extension of the transmission line. The result shows that, if the distance between national electricity network and the GSM base station location where the hybrid energy system is assumed to be installed is at a distance more than 4817 m, the installation of hybrid energy system is more economical than the electricity network. © 2008 Elsevier Ltd. All rights reserved. | URI: | https://hdl.handle.net/11499/6945 https://doi.org/10.1016/j.apenergy.2008.09.024 |
ISSN: | 0306-2619 |
Appears in Collections: | Mühendislik Fakültesi Koleksiyonu Scopus İndeksli Yayınlar Koleksiyonu / Scopus Indexed Publications Collection WoS İndeksli Yayınlar Koleksiyonu / WoS Indexed Publications Collection |
Show full item record
CORE Recommender
SCOPUSTM
Citations
128
checked on Nov 16, 2024
WEB OF SCIENCETM
Citations
101
checked on Nov 22, 2024
Page view(s)
34
checked on Aug 24, 2024
Download(s)
122
checked on Aug 24, 2024
Google ScholarTM
Check
Altmetric
Items in GCRIS Repository are protected by copyright, with all rights reserved, unless otherwise indicated.